Project Description
Oil Well equipment – Cargo Air Receivers
Air receiver – 2 pieces @ L 11.00 x W 3.20 x H 3.35 m / 28,500 kg
Platform – 2 pieces @ L 3.70 x W 1.80 x H 1.50 mr / 1,250 kg
Ladder – 2 pieces @ L 10 x W 1.3 x H 0.8 m / 1,250 kg
Spares – 1 crate @ L 0.25 x W 0.25 x H 0.10 m / 10 kg
Collection, preparation for airfreight, loading into aircraft, airfreight, landing permits, customs clearance for the cargo and the plane, off-loading (mechanics and technicians mobilised to arrival airport in order to unbolt the air receivers from the shipping saddles and bolt them back to their final saddles), and delivery to (bolted on the final saddles) to discharge site in Oben, Nigeria.
Air charter
Departure OMSJ (Sharjah International Airport) ETD 2330 26112014
Arrival DNPO (Port Harcourt International Airport) ETA 0600 27112014
Aircraft AN 124-100
Clearance and entry permits were obtained through airport security and cargo handling agencies.
Airside passes for personnel and equipment to access airport perimeter were arranged by WELL.
Pre-clearance has been arranged for the aircraft and the cargo.
Customs duty estimated prepaid to Customs for and on behalf of consignee to facilitate timely completion of clearance process and release of the cargo by Nigerian Customs for delivery to final destination in Oben.
Transport means (1 x lowbed and 1 x flatbed) and lifting equipment (mobile cranes) were positioned at arrival airport simultaneously to aircraft landing to perform direct offloading the Air receivers from the aircraft on to transport means within 3 hours free time from demurrage upon plane landing.
Coordinate clearance and handling operations with various authorities – Customs, FAAN (tarmac and airport perimeter security), NAHCO (airport handling agency), Aircraft handling agent, etc. in Port Harcourt, Nigeria in order to enable all permits and passed are issued to transport means, operators and engineers, the shipment and the aircraft are cleared in a very short time to avoid incurring aircraft demurrage charges, safely and correctly off0load the heavy, out-of gauge cargo from the aircraft and load / secure on a special transport to destination with poor quality access road to the site.
Cargo and aircraft clearances completed on time; aircraft released to take off without delay and the cargo delivered to final address on time and within budget agreed with customer.
Testimonials
“Many thanks to WELL Dubai, WELL Nigeria, Joe-Eboje and Exterran Nigeria team to make this successful timely and safe delivery.
There were challenges but together we made it possible. Congratulations!!
Thanks & Regards,
Suhas Khadke
Exterran Eastern Hemisphere Fze”
“Thanks to everyone.
WELL for ensuring all issues were sorted pretty well and for delivering on their promise.
Best Regards,
Georgina Ikebudu
Supply chain Manager
Exterran Nigeria”
“Dear All –
Let me be the first to CONGRATULATE every one for a JOB WELL DONE! I have always known that we can do it collectively as a team and get the desired result.. and we have just demonstrated that.
Thanks to the WELL team in Dubai for proper coordinating of the Dubai end of things and to the WELL team in Nigeria for timely execution of the Nigeria end regardless of the challenges.
Thanks again for all your supports and remember to always and always WORK SAFE!
Regards,
Casimir
Exterran Nigeria”